Project Management Formula Cheat Sheet
Earned value, schedule, agile, cost, and risk formulas organized for certification prep. Print it, save it, and use it for focused revision.
Showing 17 of 43 formulas — upgrade to Premium for the complete set
1. Cost Variance (CV)
CV = EV - ACCost variance measures whether completed work is costing more or less than planned.
Example
If EV = 120 and AC = 135, then CV = -15, which means the project is over budget.
Negative CV means over budget. Positive CV means under budget.
2. Schedule Variance (SV)
SV = EV - PVSchedule variance shows whether the project has earned more or less value than planned at a point in time.
Example
If EV = 90 and PV = 110, then SV = -20, which means the project is behind schedule.
Premium Only
Unlock this formula3. Estimate at Completion (EAC) — Typical
EAC = BAC / CPIUse this version of EAC when current cost performance is expected to continue for the rest of the project.
Example
If BAC = 200,000 and CPI = 0.90, then EAC = 222,222.
Premium Only
Unlock this formula4. EAC — Atypical Variance
EAC = AC + (BAC - EV)Use when past variances are not expected to recur. Assumes remaining work will be completed at the original budgeted rate.
Premium Only
Unlock this formula5. EAC — Both Cost & Schedule
EAC = AC + [(BAC - EV) / (CPI × SPI)]Use when both cost and schedule performance need to be factored into the forecast.
Premium Only
Unlock this formula6. Estimate to Complete (ETC)
ETC = EAC - ACEstimate to complete shows how much additional money will be needed from now to finish the work.
Premium Only
Unlock this formula7. To-Complete Performance Index (TCPI)
TCPI = (BAC - EV) / (BAC - AC)TCPI shows the cost efficiency needed on remaining work to meet the original budget. Values above 1.0 mean you must be more efficient.
If the denominator uses EAC instead of BAC, you're measuring against a revised budget.
8. Planned Value (PV)
PV = BAC × Planned % CompletePlanned value represents the authorized budget for work scheduled to be completed by a given date.
Example
If BAC = 100,000 and you planned to be 40% done, PV = 40,000.
9. Earned Value (EV)
EV = BAC × Actual % CompleteEarned value represents the authorized budget for work actually completed.
Example
If BAC = 100,000 and 35% of work is done, EV = 35,000.
Get the Complete Formula Cheat Sheet
Premium members get access to all 43 formulas, printable PDF export, and extra study notes that aren't available anywhere else.
Unlock Premium Access