Microsoft Project Certification Exam Topics Cover:
Overview of Project Management and Microsoft Project
Navigating the Microsoft Project Interface
Understanding Project Types and Templates
Setting Up the Project Environment
Creating and Managing Project Calendars
Inputting and Organizing Tasks
Establishing Task Dependencies (Predecessors and Successors)
Setting Task Constraints and Deadlines
Defining and Assigning Resources (Work, Material, and Cost Resources)
Resource Calendars and Availability
Managing Resource Allocation and Over-allocation
Setting and Managing Baselines
Updating Project Progress (Tasks, Durations, Percent Complete)
Tracking Work, Cost, and Schedule Variance
Using the Tracking Gantt and other Views
Using Task Types and Effort-Driven Scheduling
Task Inspector and Task Drivers
Resource Workload Management
Resource Pools and Sharing Resources across Projects
Setting Cost Rates and Tables for Resources
Cost Estimation and Budgeting
Tracking Costs and Managing Cost Variance
Applying Earned Value Analysis (EVA)
Generating Standard and Custom Reports
Visual Reports and Dashboards
Customizing Views and Tables
Using Filters, Groups, and Highlights
Integrating with Microsoft Office (Excel, Outlook, SharePoint)
Project Online and Project Server Integration
Collaborating with Teams using Project for the Web
Developing Custom Views and Gantt Charts
Macros and VBA for Automation
Optimizing Project Schedules and Resource Utilization
Definition and Importance of Project Management
Key Project Management Concepts
Introduction to Microsoft Project and Its Versions
Navigating the Microsoft Project Interface
Understanding the Ribbon, Tabs, and Commands
Customizing the Quick Access Toolbar
Understanding Project Types and Templates
Differences Between Blank Projects, Templates, and Existing Projects
Selecting and Customizing Templates for Different Project Types
Setting Project Start and Finish Dates
Configuring Project Properties
Setting Up the Project Environment
Project Options and Settings
Establishing Project Standards and Preferences
Creating and Managing Project Calendars
Base Calendars, Resource Calendars, and Task Calendars
Modifying Working and Non-working Time
Inputting and Organizing Tasks
Creating, Editing, and Deleting Tasks
Outlining Tasks and Creating Summary Tasks
Using the Task Information Dialog Box
Defining and Assigning Milestones
Incorporating Milestones into the Project Schedule
Establishing Task Dependencies
Types of Dependencies: Finish-to-Start, Start-to-Start, Finish-to-Finish, Start-to-Finish
Managing Dependencies Using the Gantt Chart and Network Diagram
Setting Task Constraints and Deadlines
Applying and Managing Deadlines
Defining and Assigning Resources
Types of Resources: Work, Material, and Cost
Creating Resource Lists and Assigning Resources to Tasks
Resource Calendars and Availability
Setting Up and Managing Resource Calendars
Specifying Resource Availability and Work Hours
Managing Resource Allocation and Over-allocation
Identifying Over-allocated Resources
Techniques for Resolving Over-allocations
Manual and Automatic Resource Leveling
Strategies for Effective Resource Leveling
Setting and Managing Baselines
Importance of Baselines in Project Tracking
Creating and Managing Multiple Baselines
Updating Project Progress
Techniques for Updating Task Progress
Actual Work, Actual Duration, and Percent Complete
Tracking Work, Cost, and Schedule Variance
Understanding Variance and Its Implications
Analyzing and Interpreting Variance Data
Using the Tracking Gantt and other Views
Overview of Tracking Gantt and Its Features
Utilizing Different Views for Effective Project Tracking
Creating and Using Interim Plans for Project Tracking
Using Task Types and Effort-Driven Scheduling
Understanding Fixed Units, Fixed Duration, and Fixed Work
Applying Effort-Driven Scheduling Principles
Task Inspector and Task Drivers
Using the Task Inspector for Task Analysis
Identifying and Managing Task Drivers
Splitting Tasks to Reflect Real-world Interruptions
Managing Split Tasks in the Schedule
Creating and Managing Recurring Tasks
Setting Up Recurrence Patterns and Exceptions
Overview of the Team Planner View
Managing Team Assignments and Workload
Resource Workload Management
Techniques for Managing Resource Workloads
Balancing Workloads Across Resources
Resource Pools and Sharing Resources across Projects
Creating and Managing Resource Pools
Sharing Resources Across Multiple Projects
Setting Cost Rates and Tables for Resources
Defining Cost Rates and Tables
Applying Different Cost Rates to Resources
Cost Estimation and Budgeting
Techniques for Estimating Costs
Creating and Managing Project Budgets
Tracking Costs and Managing Cost Variance
Updating and Tracking Project Costs
Analyzing Cost Variance and Taking Corrective Actions
Applying Earned Value Analysis (EVA)
Overview of Earned Value Management (EVM)
Key Metrics: EV, PV, AC, SV, CV, SPI, and CPI
Interpreting EVA Data for Project Performance
Generating Standard and Custom Reports
Overview of Reporting Capabilities in Microsoft Project
Creating and Customizing Reports
Visual Reports and Dashboards
Using Visual Reports for Data Analysis
Creating Dashboards for Project Monitoring
Customizing Views and Tables
Modifying and Creating Custom Views
Customizing Tables to Display Relevant Data
Using Filters, Groups, and Highlights
Applying Filters to Focus on Specific Data
Grouping Data for Better Organization
Highlighting Key Information in Project Views
Integrating with Microsoft Office
Exporting and Importing Data with Excel
Linking Tasks and Meetings with Outlook
Collaborating Using SharePoint
Project Online and Project Server Integration
Overview of Project Online and Project Server
Managing Projects and Resources in a Cloud Environment
Collaborating with Teams using Project for the Web
Using Project for the Web for Team Collaboration
Integrating Microsoft Teams for Enhanced Communication
Custom Fields and Custom Tables
Creating and Managing Custom Fields
Developing Custom Tables for Data Management
Developing Custom Views and Gantt Charts
Designing Custom Views to Meet Project Needs
Creating Custom Gantt Chart Formats
Macros and VBA for Automation
Introduction to Macros and VBA
Developing and Implementing Macros for Project Automation
Optimizing Project Schedules and Resource Utilization
Techniques for Schedule Optimization
Strategies for Efficient Resource Utilization
Real-world Project Management Scenarios
Applying Microsoft Project to Real-world Projects
Addressing Common Project Management Challenges
Case Studies and Problem-solving Exercises
Analyzing Case Studies to Apply Theoretical Knowledge
Solving Practical Problems Using Microsoft Project
Scenario-based Questions and Solutions
Practice with Scenario-based Questions
Detailed Explanations and Solutions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
Sarah is managing a large-scale construction project using Microsoft Project. She needs to create a custom Gantt Chart view that highlights critical tasks in red, displays milestones with a specific symbol, and shows tasks that are 50% complete or less in yellow.
Which of the following steps should Sarah take to achieve this?Correct
Sarah should use the Format tab to apply bar styles for critical tasks, milestones, and tasks that are 50% complete or less. This approach ensures that the custom formatting is applied correctly and consistently. According to Microsoft Project guidelines, the Format tab provides tools to customize Gantt Chart views effectively by using bar styles and filters.
Incorrect
Sarah should use the Format tab to apply bar styles for critical tasks, milestones, and tasks that are 50% complete or less. This approach ensures that the custom formatting is applied correctly and consistently. According to Microsoft Project guidelines, the Format tab provides tools to customize Gantt Chart views effectively by using bar styles and filters.
-
Question 2 of 30
2. Question
John needs to automate the process of updating project statuses in Microsoft Project. He decides to create a macro that will update the status of all tasks based on their completion percentage.
Which of the following VBA code snippets should John use to create this macro?Correct
The correct VBA code snippet is a. The correct property for updating the status of tasks based on their completion percentage is Task.Status. VBA for Microsoft Project uses the PercentComplete and Status properties to automate such updates. The other options use incorrect or non-existent properties.
Incorrect
The correct VBA code snippet is a. The correct property for updating the status of tasks based on their completion percentage is Task.Status. VBA for Microsoft Project uses the PercentComplete and Status properties to automate such updates. The other options use incorrect or non-existent properties.
-
Question 3 of 30
3. Question
Maria is tasked with optimizing her project schedule to ensure resources are not over-allocated. She uses the Resource Leveling feature in Microsoft Project.
Correct
Resource leveling in Microsoft Project delays tasks until resources become available, which can extend the project duration. This feature ensures that resources are not over-allocated by adjusting the schedule. Microsoft Project guidelines indicate that resource leveling helps manage resource constraints by balancing workload, though it may result in longer project timelines.
Incorrect
Resource leveling in Microsoft Project delays tasks until resources become available, which can extend the project duration. This feature ensures that resources are not over-allocated by adjusting the schedule. Microsoft Project guidelines indicate that resource leveling helps manage resource constraints by balancing workload, though it may result in longer project timelines.
-
Question 4 of 30
4. Question
Which of the following best defines project management and its importance?
Correct
Project management is the process of allocating resources to a series of tasks to achieve a specific goal within a set timeframe and budget. This definition aligns with the Project Management Institute (PMI) standards, emphasizing the importance of achieving project objectives while managing constraints such as time, cost, and resources.
Incorrect
Project management is the process of allocating resources to a series of tasks to achieve a specific goal within a set timeframe and budget. This definition aligns with the Project Management Institute (PMI) standards, emphasizing the importance of achieving project objectives while managing constraints such as time, cost, and resources.
-
Question 5 of 30
5. Question
What is the Critical Path Method (CPM) in project management?
Correct
The Critical Path Method (CPM) is a scheduling technique used to determine the longest path of dependent tasks in a project. This method helps identify tasks that directly impact the project’s completion time. According to PMI guidelines, CPM is crucial for effective project time management and schedule optimization.
Incorrect
The Critical Path Method (CPM) is a scheduling technique used to determine the longest path of dependent tasks in a project. This method helps identify tasks that directly impact the project’s completion time. According to PMI guidelines, CPM is crucial for effective project time management and schedule optimization.
-
Question 6 of 30
6. Question
David is considering which version of Microsoft Project to use for his organization. He needs a version that supports collaboration, resource management, and advanced reporting features.
Correct
Microsoft Project Online offers robust collaboration, resource management, and advanced reporting features, making it the best choice for David’s organization. According to Microsoft guidelines, Project Online provides comprehensive project management capabilities accessible from any device, supporting team collaboration and advanced analytics.
Incorrect
Microsoft Project Online offers robust collaboration, resource management, and advanced reporting features, making it the best choice for David’s organization. According to Microsoft guidelines, Project Online provides comprehensive project management capabilities accessible from any device, supporting team collaboration and advanced analytics.
-
Question 7 of 30
7. Question
Emily is new to Microsoft Project and needs to navigate the interface efficiently. She wants to find where she can add new tasks and link them with dependencies.
Which part of the Microsoft Project interface should Emily use?Correct
Emily should use the Task tab in the Ribbon to add new tasks and link them with dependencies. The Task tab contains essential tools for task management, including options for creating tasks, setting dependencies, and adjusting task details. Microsoft Project guidelines indicate that the Task tab is the primary location for managing project tasks.
Incorrect
Emily should use the Task tab in the Ribbon to add new tasks and link them with dependencies. The Task tab contains essential tools for task management, including options for creating tasks, setting dependencies, and adjusting task details. Microsoft Project guidelines indicate that the Task tab is the primary location for managing project tasks.
-
Question 8 of 30
8. Question
What is the purpose of the Quick Access Toolbar in Microsoft Project?
Correct
The Quick Access Toolbar provides quick access to frequently used commands and tools, enhancing user efficiency. According to Microsoft Project guidelines, users can customize the Quick Access Toolbar to include shortcuts to essential functions, improving navigation and productivity.
Incorrect
The Quick Access Toolbar provides quick access to frequently used commands and tools, enhancing user efficiency. According to Microsoft Project guidelines, users can customize the Quick Access Toolbar to include shortcuts to essential functions, improving navigation and productivity.
-
Question 9 of 30
9. Question
Alex wants to add the “Save As” command to his Quick Access Toolbar in Microsoft Project for quicker access.
Correct
Alex can right-click the Quick Access Toolbar and select “Customize Quick Access Toolbar,” then add the “Save As” command. This method aligns with Microsoft Project guidelines for customizing the toolbar, providing quick access to commonly used commands.
Incorrect
Alex can right-click the Quick Access Toolbar and select “Customize Quick Access Toolbar,” then add the “Save As” command. This method aligns with Microsoft Project guidelines for customizing the toolbar, providing quick access to commonly used commands.
-
Question 10 of 30
10. Question
When should a project manager use a template in Microsoft Project?
Correct
A project manager should use a template when starting a new project with a similar structure to previous projects to save time and ensure consistency. Microsoft Project guidelines recommend using templates to streamline project setup, maintain standard practices, and enhance efficiency by reusing existing project frameworks.
Incorrect
A project manager should use a template when starting a new project with a similar structure to previous projects to save time and ensure consistency. Microsoft Project guidelines recommend using templates to streamline project setup, maintain standard practices, and enhance efficiency by reusing existing project frameworks.
-
Question 11 of 30
11. Question
Mr. Anderson is managing a new project and needs to set a unique project calendar to account for regional holidays and specific working hours for his team.
Which calendar type should Mr. Anderson use to define these unique working and non-working times?Correct
A Base Calendar is used to set the general working and non-working times for the entire project. It can include regional holidays and specific working hours that apply to the entire team. Resource Calendars and Task Calendars can be derived from the Base Calendar to accommodate specific resources or tasks, but the Base Calendar provides the foundation. Configuring the Base Calendar is an essential step to ensure that the project schedule accurately reflects the working constraints.
Incorrect
A Base Calendar is used to set the general working and non-working times for the entire project. It can include regional holidays and specific working hours that apply to the entire team. Resource Calendars and Task Calendars can be derived from the Base Calendar to accommodate specific resources or tasks, but the Base Calendar provides the foundation. Configuring the Base Calendar is an essential step to ensure that the project schedule accurately reflects the working constraints.
-
Question 12 of 30
12. Question
When configuring a new project, you need to ensure that all settings align with company standards.
Which feature in Microsoft Project allows you to establish project standards and preferences?Correct
Project Options in Microsoft Project is where you configure various settings and preferences that apply to the entire project. This includes defining project standards such as default task types, scheduling options, and currency settings. Establishing these preferences at the start helps ensure consistency and adherence to company standards throughout the project lifecycle.
Incorrect
Project Options in Microsoft Project is where you configure various settings and preferences that apply to the entire project. This includes defining project standards such as default task types, scheduling options, and currency settings. Establishing these preferences at the start helps ensure consistency and adherence to company standards throughout the project lifecycle.
-
Question 13 of 30
13. Question
Ms. Davis has a project that involves resources from different departments, each with its own working hours. She needs to set up these varied schedules in her project plan.
Which type of calendar should she use to accurately represent these different schedules?Correct
A Resource Calendar is used to define the working times for individual resources. Since different departments have different working hours, Ms. Davis should use Resource Calendars to reflect these variations. This allows the project plan to accurately account for the availability of each resource, ensuring proper scheduling and resource allocation.
Incorrect
A Resource Calendar is used to define the working times for individual resources. Since different departments have different working hours, Ms. Davis should use Resource Calendars to reflect these variations. This allows the project plan to accurately account for the availability of each resource, ensuring proper scheduling and resource allocation.
-
Question 14 of 30
14. Question
In setting up a new project, you want to customize a template to fit a specific type of project your company frequently undertakes.
What is the first step in selecting and customizing a template for a specific project type?Correct
The first step in customizing a template is to open the template and configure the project properties. This includes setting basic project information such as the project name, manager, and any specific details unique to the project type. Configuring these properties ensures that the template is tailored to the specific requirements of the project.
Incorrect
The first step in customizing a template is to open the template and configure the project properties. This includes setting basic project information such as the project name, manager, and any specific details unique to the project type. Configuring these properties ensures that the template is tailored to the specific requirements of the project.
-
Question 15 of 30
15. Question
Mr. Johnson is tasked with managing a project that has a strict deadline. He wants to ensure that any changes to the project schedule are immediately reflected in the project finish date.
Which setting should Mr. Johnson configure to ensure that the project finish date updates automatically with schedule changes?Correct
Enabling Automatic Calculation Mode ensures that any changes made to the project schedule are immediately reflected in the project’s finish date. This mode recalculates the project schedule dynamically, providing Mr. Johnson with an up-to-date view of the project timeline. This is crucial for projects with strict deadlines as it allows for prompt adjustments and accurate tracking.
Incorrect
Enabling Automatic Calculation Mode ensures that any changes made to the project schedule are immediately reflected in the project’s finish date. This mode recalculates the project schedule dynamically, providing Mr. Johnson with an up-to-date view of the project timeline. This is crucial for projects with strict deadlines as it allows for prompt adjustments and accurate tracking.
-
Question 16 of 30
16. Question
You need to set a project start date before adding any tasks to your project plan.
Where can you set the project start date in Microsoft Project?Correct
The Project Information dialog box is where you set the project start date. This is one of the first steps in creating a new project, as it establishes the baseline from which all tasks and schedules are planned. Setting the start date accurately is crucial for proper timeline management and task scheduling.
Incorrect
The Project Information dialog box is where you set the project start date. This is one of the first steps in creating a new project, as it establishes the baseline from which all tasks and schedules are planned. Setting the start date accurately is crucial for proper timeline management and task scheduling.
-
Question 17 of 30
17. Question
Ms. Lee is preparing a project template for future use. She needs to ensure that the template can be easily adapted for various project types within her organization.
What is the most effective way to create a flexible and adaptable project template?Correct
Including generic resources in a project template makes it more flexible and adaptable for various project types. Generic resources can be replaced with specific resources when the template is used for a particular project. This approach allows the template to serve as a versatile starting point, saving time and maintaining consistency across different projects.
Incorrect
Including generic resources in a project template makes it more flexible and adaptable for various project types. Generic resources can be replaced with specific resources when the template is used for a particular project. This approach allows the template to serve as a versatile starting point, saving time and maintaining consistency across different projects.
-
Question 18 of 30
18. Question
When setting up the project environment, it is important to define working and non-working days.
Which feature in Microsoft Project allows you to modify the working and non-working time for the entire project?Correct
The Project Calendar in Microsoft Project is used to define the overall working and non-working time for the entire project. This includes setting standard working hours, weekends, and holidays. Modifying the Project Calendar ensures that the project schedule accurately reflects the availability of workdays and non-workdays.
Incorrect
The Project Calendar in Microsoft Project is used to define the overall working and non-working time for the entire project. This includes setting standard working hours, weekends, and holidays. Modifying the Project Calendar ensures that the project schedule accurately reflects the availability of workdays and non-workdays.
-
Question 19 of 30
19. Question
Mr. Patel needs to manage a project with multiple tasks that must adhere to a specific sequence.
Which feature should he use to establish task dependencies to ensure tasks are scheduled in the correct order?Correct
Task Dependencies in Microsoft Project allow Mr. Patel to link tasks together in a specific sequence, ensuring they are scheduled in the correct order. This feature is crucial for managing complex projects where the timing of tasks is interdependent. By setting dependencies, he can create a logical flow of tasks and manage the project schedule more effectively.
Incorrect
Task Dependencies in Microsoft Project allow Mr. Patel to link tasks together in a specific sequence, ensuring they are scheduled in the correct order. This feature is crucial for managing complex projects where the timing of tasks is interdependent. By setting dependencies, he can create a logical flow of tasks and manage the project schedule more effectively.
-
Question 20 of 30
20. Question
In order to create a new project, you need to select between creating a blank project, using a template, or starting from an existing project.
What is one advantage of starting a project from an existing project?Correct
Starting a project from an existing project allows you to leverage predefined tasks and resources, which can save time and ensure consistency. This approach is beneficial for projects that are similar in scope and structure to previous projects, as it reduces the effort required to set up the new project and ensures that established best practices are followed.
Incorrect
Starting a project from an existing project allows you to leverage predefined tasks and resources, which can save time and ensure consistency. This approach is beneficial for projects that are similar in scope and structure to previous projects, as it reduces the effort required to set up the new project and ensures that established best practices are followed.
-
Question 21 of 30
21. Question
Mr. Smith is managing a new project and needs to input a series of tasks into Microsoft Project. One of the tasks, “Develop Prototype,” is crucial and needs to be broken down into smaller tasks to better manage and track its progress. What should Mr. Smith do to effectively organize these tasks?
Correct
In Microsoft Project, creating a summary task allows Mr. Smith to group related smaller tasks under a single, higher-level task. This approach provides a clear structure, making it easier to track progress and manage dependencies. Reference: Microsoft Project 2019 Step by Step, Chapter 4: Organizing Tasks.
Incorrect
In Microsoft Project, creating a summary task allows Mr. Smith to group related smaller tasks under a single, higher-level task. This approach provides a clear structure, making it easier to track progress and manage dependencies. Reference: Microsoft Project 2019 Step by Step, Chapter 4: Organizing Tasks.
-
Question 22 of 30
22. Question
Which of the following actions is NOT a correct method for deleting a task in Microsoft Project?
Correct
There is no “Remove Task” option in the Task Information Dialog Box. Tasks can be deleted by right-clicking, using the “Delete” key, or via the “Task” tab. Reference: Microsoft Project 2019 Inside Out, Chapter 5: Managing Tasks.
Incorrect
There is no “Remove Task” option in the Task Information Dialog Box. Tasks can be deleted by right-clicking, using the “Delete” key, or via the “Task” tab. Reference: Microsoft Project 2019 Inside Out, Chapter 5: Managing Tasks.
-
Question 23 of 30
23. Question
Ms. Johnson is working on a project plan where she needs to group several related tasks under a single heading to improve organization and reporting. How should she proceed?
Correct
Indenting tasks in Microsoft Project creates a summary task, which groups related tasks and improves project structure. This method is essential for effective project management and reporting. Reference: Microsoft Project 2019 Step by Step, Chapter 4: Organizing Tasks.
Incorrect
Indenting tasks in Microsoft Project creates a summary task, which groups related tasks and improves project structure. This method is essential for effective project management and reporting. Reference: Microsoft Project 2019 Step by Step, Chapter 4: Organizing Tasks.
-
Question 24 of 30
24. Question
Which tab in the Task Information Dialog Box allows you to set a task’s duration and start/finish dates?
Correct
The “General” tab in the Task Information Dialog Box allows users to set the task’s duration, start, and finish dates. Reference: Microsoft Project 2019 Inside Out, Chapter 5: Managing Tasks.
Incorrect
The “General” tab in the Task Information Dialog Box allows users to set the task’s duration, start, and finish dates. Reference: Microsoft Project 2019 Inside Out, Chapter 5: Managing Tasks.
-
Question 25 of 30
25. Question
Mr. Patel is managing a software development project and needs to mark the completion of the design phase as a milestone. How can he define and assign this milestone in Microsoft Project?
Correct
Milestones in Microsoft Project are defined as tasks with zero duration. They represent significant events or achievements in the project timeline. Reference: Microsoft Project 2019 Step by Step, Chapter 5: Defining and Assigning Milestones.
Incorrect
Milestones in Microsoft Project are defined as tasks with zero duration. They represent significant events or achievements in the project timeline. Reference: Microsoft Project 2019 Step by Step, Chapter 5: Defining and Assigning Milestones.
-
Question 26 of 30
26. Question
What is the primary purpose of incorporating milestones into a project schedule?
Correct
Milestones are used to mark significant points or events in a project, such as the completion of a phase or delivery of a key deliverable. Reference: Microsoft Project 2019 Inside Out, Chapter 5: Managing Milestones.
Incorrect
Milestones are used to mark significant points or events in a project, such as the completion of a phase or delivery of a key deliverable. Reference: Microsoft Project 2019 Inside Out, Chapter 5: Managing Milestones.
-
Question 27 of 30
27. Question
Ms. Garcia is working on a construction project and needs to establish dependencies between tasks. For example, “Pour Foundation” must be completed before “Build Walls” can start. Which type of dependency should she use?
Correct
The Finish-to-Start (FS) dependency type means that the successor task (Build Walls) cannot start until the predecessor task (Pour Foundation) is finished. This is the most common dependency type. Reference: Microsoft Project 2019 Step by Step, Chapter 6: Establishing Task Dependencies.
Incorrect
The Finish-to-Start (FS) dependency type means that the successor task (Build Walls) cannot start until the predecessor task (Pour Foundation) is finished. This is the most common dependency type. Reference: Microsoft Project 2019 Step by Step, Chapter 6: Establishing Task Dependencies.
-
Question 28 of 30
28. Question
Which type of dependency allows two tasks to start simultaneously?
Correct
The Start-to-Start (SS) dependency allows two tasks to begin at the same time. This type of dependency is useful when tasks can be performed in parallel. Reference: Microsoft Project 2019 Inside Out, Chapter 6: Managing Dependencies.
Incorrect
The Start-to-Start (SS) dependency allows two tasks to begin at the same time. This type of dependency is useful when tasks can be performed in parallel. Reference: Microsoft Project 2019 Inside Out, Chapter 6: Managing Dependencies.
-
Question 29 of 30
29. Question
Mr. Lee is reviewing his project’s schedule using the Gantt Chart. He notices that several tasks are not starting as planned due to dependency issues. What should he do to manage these dependencies more effectively?
Correct
The Network Diagram view provides a visual representation of task dependencies, making it easier to identify and adjust any issues. This view helps in managing complex dependencies more effectively. Reference: Microsoft Project 2019 Inside Out, Chapter 6: Managing Dependencies.
Incorrect
The Network Diagram view provides a visual representation of task dependencies, making it easier to identify and adjust any issues. This view helps in managing complex dependencies more effectively. Reference: Microsoft Project 2019 Inside Out, Chapter 6: Managing Dependencies.
-
Question 30 of 30
30. Question
What is the difference between a task constraint and a deadline in Microsoft Project?
Correct
Task constraints impact how and when a task is scheduled, while deadlines serve as markers indicating when a task should be completed without affecting its scheduling. Reference: Microsoft Project 2019 Step by Step, Chapter 7: Setting Task Constraints and Deadlines.
Incorrect
Task constraints impact how and when a task is scheduled, while deadlines serve as markers indicating when a task should be completed without affecting its scheduling. Reference: Microsoft Project 2019 Step by Step, Chapter 7: Setting Task Constraints and Deadlines.