Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
The Scrum Team is working on a project that involves frequent changes in stakeholder requirements. The team finds it challenging to adapt to these changes while maintaining their focus on the Sprint Goal. What should the Scrum Master do to help the team manage these changes effectively?
Correct
The Scrum Master should facilitate a discussion with the team and stakeholders to evaluate the current approach to managing technical debt, identify issues, and collaboratively develop a revised strategy. This approach ensures that concerns are addressed and a more effective strategy is developed through collaboration.
Incorrect
The Scrum Master should facilitate a discussion with the team and stakeholders to evaluate the current approach to managing technical debt, identify issues, and collaboratively develop a revised strategy. This approach ensures that concerns are addressed and a more effective strategy is developed through collaboration.
-
Question 2 of 30
2. Question
Sophia, a Scrum Master, notices that the Development Team is frequently missing Sprint Goals due to unplanned work that arises mid-Sprint. How should Sophia handle this situation to help the team improve their focus and adherence to Sprint Goals?
Correct
Sophia should facilitate a session to discuss and establish a process for handling unplanned work, including how to assess its impact on the Sprint Goal and manage it effectively. This approach helps the team develop a structured process for dealing with unplanned work while maintaining focus on Sprint Goals.
Incorrect
Sophia should facilitate a session to discuss and establish a process for handling unplanned work, including how to assess its impact on the Sprint Goal and manage it effectively. This approach helps the team develop a structured process for dealing with unplanned work while maintaining focus on Sprint Goals.
-
Question 3 of 30
3. Question
The Scrum Team is experiencing frequent conflicts during Sprint Retrospectives, which are impacting the effectiveness of the session. What should the Scrum Master do to address these conflicts and improve the Retrospective process?
Correct
The Scrum Master should intervene during conflicts by mediating and facilitating discussions to help the team resolve differences and focus on constructive feedback. This approach helps in addressing conflicts effectively and improving the overall Retrospective process.
Incorrect
The Scrum Master should intervene during conflicts by mediating and facilitating discussions to help the team resolve differences and focus on constructive feedback. This approach helps in addressing conflicts effectively and improving the overall Retrospective process.
-
Question 4 of 30
4. Question
The Scrum Team is working on a highly complex project with multiple dependencies between teams. The Scrum Master is concerned about the integration of work across teams. What is the best approach for the Scrum Master to ensure effective integration and collaboration across teams?
Correct
The Scrum Master should schedule regular integration meetings between teams to discuss dependencies and coordinate integration efforts. This approach facilitates communication and coordination across teams, ensuring effective integration of work.
Incorrect
The Scrum Master should schedule regular integration meetings between teams to discuss dependencies and coordinate integration efforts. This approach facilitates communication and coordination across teams, ensuring effective integration of work.
-
Question 5 of 30
5. Question
The Scrum Team has been consistently missing their Sprint Goals due to challenges in accurately estimating the effort required for backlog items. What should the Scrum Master do to help the team improve their estimation accuracy?
Correct
The Scrum Master should encourage the team to use multiple estimation techniques and experiment with different methods to determine which one yields the most accurate results. This approach helps the team refine their estimation process and find the most effective method for their context.
Incorrect
The Scrum Master should encourage the team to use multiple estimation techniques and experiment with different methods to determine which one yields the most accurate results. This approach helps the team refine their estimation process and find the most effective method for their context.
-
Question 6 of 30
6. Question
The Scrum Team is experiencing difficulties with cross-functional collaboration, with team members working in silos and not sharing knowledge or skills. What action should the Scrum Master take to enhance cross-functional collaboration?
Correct
The Scrum Master should implement pair programming and cross-training sessions to encourage team members to work together and share their expertise. This approach helps break down silos and fosters a collaborative environment where team members can leverage each other’s skills and knowledge.
Incorrect
The Scrum Master should implement pair programming and cross-training sessions to encourage team members to work together and share their expertise. This approach helps break down silos and fosters a collaborative environment where team members can leverage each other’s skills and knowledge.
-
Question 7 of 30
7. Question
John, a Scrum Master, notices that the Development Team is facing difficulties with managing dependencies between their work and other teams’ work. These dependencies are causing delays and impacting their ability to meet Sprint Goals. What should John do to address this issue?
Correct
John should work with the other Scrum Masters to coordinate dependencies and align schedules to minimize delays and ensure that dependencies are managed effectively. This approach facilitates collaboration between teams and helps manage dependencies in a coordinated manner.
Incorrect
John should work with the other Scrum Masters to coordinate dependencies and align schedules to minimize delays and ensure that dependencies are managed effectively. This approach facilitates collaboration between teams and helps manage dependencies in a coordinated manner.
-
Question 8 of 30
8. Question
The Scrum Team has successfully delivered several Sprints but has noticed that the quality of the deliverables has been inconsistent. What should the Scrum Master do to improve the quality of deliverables?
Correct
The Scrum Master should work with the team to enhance their Definition of Done (DoD) by including specific quality criteria and ensuring that all team members adhere to it. This approach ensures that quality expectations are clear and consistently met for each deliverable.
Incorrect
The Scrum Master should work with the team to enhance their Definition of Done (DoD) by including specific quality criteria and ensuring that all team members adhere to it. This approach ensures that quality expectations are clear and consistently met for each deliverable.
-
Question 9 of 30
9. Question
The Scrum Team is using a Kanban board to manage their workflow but has encountered issues with bottlenecks and delays in completing tasks. What should the Scrum Master do to address these issues?
Correct
The Scrum Master should introduce WIP (Work In Progress) limits to the Kanban board to help identify and manage bottlenecks more effectively. WIP limits help the team focus on completing tasks before starting new ones, which can improve flow and reduce delays.
Incorrect
The Scrum Master should introduce WIP (Work In Progress) limits to the Kanban board to help identify and manage bottlenecks more effectively. WIP limits help the team focus on completing tasks before starting new ones, which can improve flow and reduce delays.
-
Question 10 of 30
10. Question
During a Sprint, the Development Team discovers a major issue with the product that requires immediate attention and will impact the Sprint Goal. What should the Scrum Master do to address this situation?
Correct
The Scrum Master should facilitate a discussion with the Product Owner to determine if the issue can be addressed within the current Sprint and adjust the Sprint Goal if necessary. This approach ensures that the team addresses critical issues while maintaining alignment with Sprint objectives.
Incorrect
The Scrum Master should facilitate a discussion with the Product Owner to determine if the issue can be addressed within the current Sprint and adjust the Sprint Goal if necessary. This approach ensures that the team addresses critical issues while maintaining alignment with Sprint objectives.
-
Question 11 of 30
11. Question
The Scrum Team has noticed a recurring problem with incomplete user stories at the end of each Sprint, leading to unfulfilled Sprint Goals. What should the Scrum Master focus on to address this problem?
Correct
The Scrum Master should work with the team to refine their Sprint Planning process, ensuring that user stories are well-defined, appropriately sized, and achievable within the Sprint. This approach helps improve the likelihood of completing user stories and achieving Sprint Goals.
Incorrect
The Scrum Master should work with the team to refine their Sprint Planning process, ensuring that user stories are well-defined, appropriately sized, and achievable within the Sprint. This approach helps improve the likelihood of completing user stories and achieving Sprint Goals.
-
Question 12 of 30
12. Question
Laura, a Scrum Master, notices that the Development Team is struggling with the integration of features developed by other teams, causing delays and inefficiencies. How should Laura address this issue to improve the integration process?
Correct
Laura should establish a cross-team integration group to oversee and manage the integration process, ensuring that all teams are aligned and dependencies are handled effectively. This approach facilitates coordination and helps manage dependencies more efficiently.
Incorrect
Laura should establish a cross-team integration group to oversee and manage the integration process, ensuring that all teams are aligned and dependencies are handled effectively. This approach facilitates coordination and helps manage dependencies more efficiently.
-
Question 13 of 30
13. Question
A Scrum Team is working on a project with high complexity and frequently encounters challenges during the Sprint. What should the Scrum Master do to help the team manage this complexity more effectively?
Correct
The Scrum Master should encourage the team to break down complex backlog items into smaller, more manageable pieces and prioritize them accordingly. This approach helps the team manage complexity and make incremental progress towards completing complex features.
Incorrect
The Scrum Master should encourage the team to break down complex backlog items into smaller, more manageable pieces and prioritize them accordingly. This approach helps the team manage complexity and make incremental progress towards completing complex features.
-
Question 14 of 30
14. Question
The Scrum Team has implemented several changes in their workflow but has not seen significant improvements in their performance. What should the Scrum Master do to ensure that changes lead to meaningful improvements?
Correct
The Scrum Master should conduct a detailed review of the changes made and gather feedback from the team to identify areas where further adjustments are needed. This approach helps evaluate the effectiveness of the changes and make necessary adjustments to improve performance.
Incorrect
The Scrum Master should conduct a detailed review of the changes made and gather feedback from the team to identify areas where further adjustments are needed. This approach helps evaluate the effectiveness of the changes and make necessary adjustments to improve performance.
-
Question 15 of 30
15. Question
The Development Team has identified several technical debt issues during the current Sprint that need to be addressed. What is the best approach for the Scrum Master to help the team manage technical debt effectively?
Correct
The Scrum Master should work with the Product Owner to include technical debt items in the Product Backlog and address them during future Sprints based on their priority. This approach ensures that technical debt is managed in a structured way and aligns with the overall project priorities.
Incorrect
The Scrum Master should work with the Product Owner to include technical debt items in the Product Backlog and address them during future Sprints based on their priority. This approach ensures that technical debt is managed in a structured way and aligns with the overall project priorities.
-
Question 16 of 30
16. Question
During the Sprint Retrospective, the team identifies several potential improvements to their workflow. What should the Scrum Master do to ensure that these improvements are effectively implemented?
Correct
The Scrum Master should facilitate the team in prioritizing the identified improvements and developing actionable plans to implement the highest-priority changes in the next Sprint. This ensures that the improvements are actionable, relevant, and effectively integrated into the team’s workflow.
Incorrect
The Scrum Master should facilitate the team in prioritizing the identified improvements and developing actionable plans to implement the highest-priority changes in the next Sprint. This ensures that the improvements are actionable, relevant, and effectively integrated into the team’s workflow.
-
Question 17 of 30
17. Question
Alex, a Scrum Master, notices that the Development Team frequently gets sidetracked by urgent requests from stakeholders during the Sprint, which affects their ability to focus on Sprint Goals. What should Alex do to address this issue?
Correct
Alex should work with the Product Owner to establish a process for handling urgent requests outside of the Sprint, ensuring they are addressed in a structured manner. This approach helps manage stakeholder requests effectively without disrupting the Sprint’s focus and goals.
Incorrect
Alex should work with the Product Owner to establish a process for handling urgent requests outside of the Sprint, ensuring they are addressed in a structured manner. This approach helps manage stakeholder requests effectively without disrupting the Sprint’s focus and goals.
-
Question 18 of 30
18. Question
The Scrum Team has completed several Sprints but has noticed that their velocity is fluctuating significantly from Sprint to Sprint. What should the Scrum Master do to address this issue?
Correct
The Scrum Master should investigate potential factors contributing to the velocity fluctuations, such as changes in team composition, external dependencies, or varying backlog item complexity, and work with the team to address these factors. Understanding and addressing the root causes of velocity fluctuations helps stabilize performance and improve planning accuracy.
Incorrect
The Scrum Master should investigate potential factors contributing to the velocity fluctuations, such as changes in team composition, external dependencies, or varying backlog item complexity, and work with the team to address these factors. Understanding and addressing the root causes of velocity fluctuations helps stabilize performance and improve planning accuracy.
-
Question 19 of 30
19. Question
The Product Owner has been providing unclear or incomplete backlog items, leading to confusion and inefficiencies during Sprint Planning. What should the Scrum Master do to improve the quality of backlog items?
Correct
The Scrum Master should work with the Product Owner to establish clear guidelines for writing backlog items and provide examples of well-defined items. This approach ensures that backlog items are consistently clear and complete, improving the efficiency of Sprint Planning.
Incorrect
The Scrum Master should work with the Product Owner to establish clear guidelines for writing backlog items and provide examples of well-defined items. This approach ensures that backlog items are consistently clear and complete, improving the efficiency of Sprint Planning.
-
Question 20 of 30
20. Question
During a Sprint Review, the stakeholders provide feedback that requires significant changes to the delivered Increment. What is the most effective approach for the Scrum Master to handle this feedback?
Correct
The Scrum Master should work with the Product Owner to assess the feedback, determine the priority of the requested changes, and integrate them into the Product Backlog for future consideration. This approach ensures that the feedback is handled in a structured manner and aligns with the overall product goals and priorities.
Incorrect
The Scrum Master should work with the Product Owner to assess the feedback, determine the priority of the requested changes, and integrate them into the Product Backlog for future consideration. This approach ensures that the feedback is handled in a structured manner and aligns with the overall product goals and priorities.
-
Question 21 of 30
21. Question
A Scrum Team is experiencing difficulties with maintaining a consistent pace and frequently experiences burnout due to overcommitment. What should the Scrum Master do to address this issue?
Correct
The Scrum Master should review the team’s past performance to identify trends and adjust future Sprint commitments to align with the team’s capacity. This approach helps ensure that the team’s workload is manageable and aligns with their actual capacity, reducing the risk of burnout.
Incorrect
The Scrum Master should review the team’s past performance to identify trends and adjust future Sprint commitments to align with the team’s capacity. This approach helps ensure that the team’s workload is manageable and aligns with their actual capacity, reducing the risk of burnout.
-
Question 22 of 30
22. Question
Emma, a Scrum Master, observes that the team is struggling with integrating their work with other teams due to conflicting priorities and dependencies. How should Emma address this challenge to improve cross-team collaboration?
Correct
Emma should schedule regular cross-team meetings to discuss and coordinate priorities and dependencies, ensuring alignment among all involved teams. This approach facilitates effective communication and coordination, helping to manage and resolve conflicts related to cross-team dependencies.
Incorrect
Emma should schedule regular cross-team meetings to discuss and coordinate priorities and dependencies, ensuring alignment among all involved teams. This approach facilitates effective communication and coordination, helping to manage and resolve conflicts related to cross-team dependencies.
-
Question 23 of 30
23. Question
The Scrum Team has consistently completed their Sprint Goals but has not been able to deliver a high-quality product increment. What should the Scrum Master focus on to address this issue?
Correct
The Scrum Master should work with the team to ensure that the Definition of Done is clearly defined and adhered to for every backlog item. This approach helps ensure that each Increment meets the required quality standards and fulfills the Sprint Goal.
Incorrect
The Scrum Master should work with the team to ensure that the Definition of Done is clearly defined and adhered to for every backlog item. This approach helps ensure that each Increment meets the required quality standards and fulfills the Sprint Goal.
-
Question 24 of 30
24. Question
A new Scrum Master has joined the team and notices that team members are unclear about their roles and responsibilities within the Scrum framework. What should the Scrum Master do to address this issue?
Correct
The Scrum Master should conduct a training session for the team to clarify the roles and responsibilities within the Scrum framework and ensure everyone understands their role. This approach helps establish a clear understanding of roles and responsibilities, facilitating better collaboration and effectiveness within the team.
Incorrect
The Scrum Master should conduct a training session for the team to clarify the roles and responsibilities within the Scrum framework and ensure everyone understands their role. This approach helps establish a clear understanding of roles and responsibilities, facilitating better collaboration and effectiveness within the team.
-
Question 25 of 30
25. Question
The Development Team has identified that their Scrum Master is consistently taking on tasks that are not within the Scrum Master’s role, such as actively participating in coding and making design decisions. What impact could this have, and how should it be addressed?
Correct
The Scrum Master’s involvement in non-Scrum activities can blur role boundaries and impede their ability to effectively facilitate Scrum processes. It is important for the Scrum Master to focus solely on their facilitation and coaching role to ensure they can effectively support the team and uphold Scrum practices.
Incorrect
The Scrum Master’s involvement in non-Scrum activities can blur role boundaries and impede their ability to effectively facilitate Scrum processes. It is important for the Scrum Master to focus solely on their facilitation and coaching role to ensure they can effectively support the team and uphold Scrum practices.
-
Question 26 of 30
26. Question
During Sprint Planning, the Development Team estimates a backlog item using a story point value significantly higher than what was expected by the Product Owner. What should the Scrum Master do to address this discrepancy?
Correct
The Scrum Master should facilitate a discussion between the Product Owner and Development Team to understand the reasons for the discrepancy and reach a common understanding. This approach helps ensure that both parties align on the complexity and effort required, leading to a more accurate Sprint Backlog.
Incorrect
The Scrum Master should facilitate a discussion between the Product Owner and Development Team to understand the reasons for the discrepancy and reach a common understanding. This approach helps ensure that both parties align on the complexity and effort required, leading to a more accurate Sprint Backlog.
-
Question 27 of 30
27. Question
David, a Scrum Master, notices that the team is consistently missing their Sprint Goals due to unclear or changing requirements from the Product Owner. How should David address this situation to improve the team’s ability to meet their goals?
Correct
David should work with the Product Owner to establish a clear and stable set of requirements for each Sprint and ensure that any changes are managed through proper change control processes. This approach helps maintain focus and alignment on Sprint Goals and reduces the impact of unclear or changing requirements.
Incorrect
David should work with the Product Owner to establish a clear and stable set of requirements for each Sprint and ensure that any changes are managed through proper change control processes. This approach helps maintain focus and alignment on Sprint Goals and reduces the impact of unclear or changing requirements.
-
Question 28 of 30
28. Question
The Scrum Team has been experiencing conflicts during Daily Scrums, with team members frequently interrupting each other and arguing about task prioritization. What should the Scrum Master do to resolve this issue?
Correct
The Scrum Master should facilitate a workshop on effective communication and collaboration techniques to help the team improve their interaction during Daily Scrums. This approach addresses the root cause of conflicts and enhances the team’s ability to collaborate effectively.
Incorrect
The Scrum Master should facilitate a workshop on effective communication and collaboration techniques to help the team improve their interaction during Daily Scrums. This approach addresses the root cause of conflicts and enhances the team’s ability to collaborate effectively.
-
Question 29 of 30
29. Question
The Product Owner is often unavailable for feedback during the Sprint, leading to delays and misunderstandings about backlog items. What action should the Scrum Master take to mitigate this issue?
Correct
The Scrum Master should request that the Product Owner be more available for feedback and establish a fixed schedule for feedback sessions during the Sprint. This ensures that the Product Owner is accessible when needed and that the team can get timely feedback, which is crucial for maintaining progress and clarity.
Incorrect
The Scrum Master should request that the Product Owner be more available for feedback and establish a fixed schedule for feedback sessions during the Sprint. This ensures that the Product Owner is accessible when needed and that the team can get timely feedback, which is crucial for maintaining progress and clarity.
-
Question 30 of 30
30. Question
During a Sprint Retrospective, the Scrum Team identifies that their current definition of “Done” is too vague and leads to inconsistent quality in the increments. What is the best approach for the Scrum Master to address this issue?
Correct
The Scrum Master should facilitate a workshop with the team to review and update the Definition of Done, ensuring that it is specific and comprehensive for all types of work. This collaborative approach helps the team reach a shared understanding and agreement on what constitutes “Done,” improving the consistency and quality of increments.
Incorrect
The Scrum Master should facilitate a workshop with the team to review and update the Definition of Done, ensuring that it is specific and comprehensive for all types of work. This collaborative approach helps the team reach a shared understanding and agreement on what constitutes “Done,” improving the consistency and quality of increments.